Borehole Survey for Male’-Hulhule’ bridge project has been commenced on 20th May 2015.
Two boreholes will be drilled on land in Male side. It will take approximately 5 days to complete the boreholes in Male’.
Total 26 bore holes will be drilled including the boreholes in sea. Borehole depths ranges between 40 to 50 m. It will take approximately 20 days to complete the survey.
Topographic survey, Hydrographic survey and bathymetry survey has been completed now. Seismic reflection survey is ongoing and is expected to finish next week.