MTCC CEO and team has inspected the progress of N.Landhoo Harbor Development Project

MTCC CEO and team has inspected the progress of N.Landhoo Harbor Development Project


Estimated time to read the article : 0 min, 37 secs

Mr. Adam Adam Azim , CEO MTCC and team has inspected the progress of N.Landhoo Harbor Development Project. Scope of works for the project include dredging and excavation operations of 25,000 cbm; the construction of a 256m quay wall; a 401m breakwater and a 60m revetment. 

The Ministry of National Planning, Housing and Infrastructure contracted the MVR 32.4 million project to us on 10th December 2019. The project was mobilized on 12th August 2020.